Look-ahead and master schedule: 3WLA alongside Primavera P6 and Microsoft Project
Primavera P6 and Microsoft Project are critical-path scheduling tools built for the master schedule. 3WLA doesn't replace them. It's for the short-term plan the field works from: the 3-week look-ahead. Here's how the two fit together.
Updated 13 November 2026 · 5 min read
Different jobs
| Topic | Master schedule (P6, Microsoft Project) | 3-week look-ahead (3WLA) |
|---|---|---|
| Purpose | Whole project, contract dates, critical path | The next 21 days of field work |
| Owned by | Scheduler, project controls or PM | Superintendent with the foremen |
| Level of detail | Activities across the whole job | Tasks of a few days, by area and trade |
| Updated | Usually monthly, or as the contract requires | Every week |
| Logic | Relationships, float, resources, baselines | Dates, trade commitments, constraints |
| Who works in it | Trained schedulers with a paid licence each | Anyone on the project; viewers just open a link |
| Who reads it | Owner, PM, project controls | Field team, subcontractors, inspectors |
Why not run the look-ahead in P6?
You can filter a three-week window in P6 or Microsoft Project and print it, and many teams do. It works until the field needs more detail than the master schedule should carry.
Foremen rarely have access to the scheduling tool. Breaking activities down by area, crew and day clutters the master schedule's logic. And weekly field changes shouldn't rewrite the schedule the contract is measured against. Keeping the look-ahead separate lets the field plan in detail while the master schedule stays clean.
Keeping the two in line
Export the master schedule to PDF
From Primavera P6, Microsoft Project, Procore or similar.
Upload it to an AI comparison
On the Business plan, 3WLA reads the activities and dates and lists what is on track, moved, early or missing from your look-ahead (with a 2-day tolerance).
Review and adjust
The comparison is advisory. Decide what to change in the look-ahead, and what to raise with the scheduler.
Feed it back
Pass real field progress and slips to whoever updates the master schedule each month.
What 3WLA doesn't do
Keep those in your master schedule tool. 3WLA is the field's working plan next to it.
- Critical path logic, relationships and float.
- Resource levelling or cost loading.
- Baselines for contract schedule submissions.
Common questions
Can 3WLA import a P6 XER or Microsoft Project file?
Not directly. Export the activities you need to Excel and paste them into the grid, or upload a PDF export for an AI comparison.
Which plan includes AI comparison?
Business, with 50 comparisons a month. Failed comparisons aren't counted.
Do we need a scheduler to use 3WLA?
No. It's built for superintendents and project managers. If you can fill in a spreadsheet, you can build a look-ahead.
Run your next look-ahead in 3WLA
Free for one project, with unlimited people. Paste your rows from Excel, then issue the same schedule to every trade by email or read-only link.
Keep reading
- GuideWhat is a 3-week look-ahead schedule?What a 3-week look-ahead schedule is, who prepares it, what goes in it and how it connects to the master schedule, with an annotated example.
- Comparison3WLA vs Excel and Google SheetsSpreadsheets compared with 3WLA for 3-week look-ahead schedules: building the plan, sharing it with subcontractors, keeping one version, phones and cost.
- Free template3-week look-ahead template (Excel)Free 3-week look-ahead template for Excel and Google Sheets: a 21-day bar chart that fills itself in, work days, progress and notes. No sign-up.