How to create a 3-week look-ahead schedule: step by step, with a worked example
Seven steps from the master schedule to a plan your trades will commit to, followed through a real scope: the first pour of a Level 2 elevated slab.
Updated 14 November 2026 · 9 min read
- Layout and shore layoutSurvey
- Shores and deck formsForming
- Edge forms and blockoutsForming
- Bottom rebarRebar
- Sleeves and embedsPlumbing, electrical
- Top rebarRebar
- Pre-pour inspectionInspector
- Pour and finishConcrete
- Cure (no loads)Hold
Quick answer
To create a 3-week look-ahead schedule: pull every activity that starts or is in progress in the next 21 days from the master schedule; break each one into tasks a single crew can finish in one to five working days; give every task one trade, a start, a finish and a duration in working days; check each task for constraints and log anything not ready with an owner and a clear-by date; review it with the foremen to get commitments; then issue one version and update it every week.
Key takeaways
- Start from the current master schedule, not a blank sheet.
- One task = one crew, one area, a few days, and a finish you can see on site.
- Deliveries and inspections are tasks too; put them on the plan so they get booked.
- Clear constraints two to three weeks before the work, not on the day.
- Measure it weekly: tasks done as planned ÷ tasks planned, with a reason for every miss.
Before you start
- The latest master schedule update (and the phase or pull plan, if you have one).
- Your submittal, RFI and procurement logs: they hold most of your constraints.
- The inspection requirements for the work coming up, and how much notice the inspector needs.
- The foremen for every trade working now or starting in the next three weeks.
Step 1: Set the window and pull the work from the master schedule
Pick a start date (normally next Monday) and list every activity that starts, finishes or is in progress in the next 15 working days. Add anything later that needs action now, such as long-lead materials or a submittal that must be approved before the work can start.
In our example, the master schedule shows activity 2.1, "L2 elevated slab, pour 1", at 12 working days, starting next Monday, with pour 2 behind it.
Step 2: Break each activity into crew-sized tasks
A master schedule activity is too big to manage in the field. Break it down until each task is done by one crew, in one area, in roughly one to five working days, with a finish you can check by walking the deck. Researchers Hamzeh, Ballard and Tommelein describe this as breaking work down to "the level of operations": tasks performed by specific work crews.
Activity 2.1 becomes nine tasks: layout, shores and deck forms, edge forms, bottom rebar, sleeves and embeds, top rebar, the pre-pour inspection, the pour, and the cure. The rebar delivery goes on as its own line.
- Split a task when two trades share it, or when it runs longer than a week.
- Give hand-offs their own lines: an inspection, a delivery, an area handed over.
- New, critical or repetitive operations (a first elevated pour, say) deserve a short walkthrough with the crew before the first run.
Step 3: Fill in every column
Each column answers one question a foreman or inspector will ask.
| Column | What to write | Example |
|---|---|---|
| Task ID | The master schedule activity it comes from, plus a number | 2.1.5 |
| Activity | Verb, element, area: specific enough to check | Bottom rebar, L2 pour 1 (grids A–D), not "Rebar" |
| Trade or subcontractor | One company, ideally the foreman's crew | Northline Rebar |
| Start and finish | Working-day dates | Tue wk 2 → Wed wk 2 |
| Duration | Working days, from the project's work week | 2 days |
| Progress or status | 0–100% or not started / in progress / done / delayed / blocked | 0%, not started |
| Constraints and notes | What must be true before it starts, with an owner | Delivery Monday; PE confirms |
Step 4: Sequence it in working days
- Follow the hand-offs: each task starts when the one it depends on is done and accepted.
- Count working days, not calendar days, and leave weekends and holidays out.
- Put deliveries and inspections in as tasks with the notice they need. If the inspector needs 48 hours, the booking is a task two days before.
- Check crews against the work: if the forming crew is on edge forms, it isn't on Level 1.
Step 5: Check every task is ready (constraint screening)
Go through weeks 2 and 3 task by task and ask whether everything it needs will be there. The 2012 study recommends clearing constraints "at least two to three weeks prior to executing a task". The Lean Construction Institute's standard work adds the discipline: every constraint goes on a log with a champion who commits to clearing it and a date.
Readiness check · Pour L2 slab, pour 1
- InformationApproved drawings, answered RFIs, submittals back?RFI 14 (sleeve locations) open. Project engineer, by day 4.Log it
- MaterialsDelivered, or a confirmed delivery date before it's needed?Rebar confirmed for Monday of week 2.Ready
- LabourThe right crew, the right size, on the right days?Forming crew of six; rebar crew of four from day 7.Ready
- EquipmentBooked, on site and working?Pump and boom not booked. Concrete foreman, by day 6.Log it
- Work before itWill the previous trade be finished and signed off?Shores and deck forms finish day 4.Ready
- Space and accessRoom to work, store and get trucks in?Pump set-up on the north lane; L1 crews clear the area.Ready
- Inspections and approvalsBooked, with the notice the inspector needs?Pre-pour inspection not booked yet. Superintendent, by day 7.Log it
- If a constraint can't be cleared in time, move the task now, before anyone commits to it, and pull in work that is ready.
- In the example, the rebar can't arrive until Monday, so everything after it moves one day while it's still just a plan.
Step 6: Review it with the foremen and get commitments
Walk through the plan with the trades, week 1 first. Ask "What do you need to finish this by Friday?" rather than "Will you be done Friday?". A task only counts as committed when the foreman says the crew, materials and previous work will be there. Our guide to the weekly look-ahead meeting has a 45-minute agenda.
Step 7: Issue it, then update it every week
Issue one version
Send the same look-ahead to every trade and note what changed since last week.
Record what happened
At the end of the week, mark each committed task done or not. Percent Plan Complete is the done count divided by the committed count.
Write down why
Give every miss a reason: labour, materials, equipment, prerequisite work, design, inspection, weather.
Roll forward
Drop the finished week, carry over unfinished work, add a new week 3 from the master schedule, and screen it.
Worked example: a Level 2 slab pour, from draft to the following week
Follow pour 1 through the four stages of a look-ahead. Choose a step to see how the plan changes.
- 2.1.1Layout and shore layoutSurveyPlanned, 1 working days
- 2.1.2Shores and deck formsFormingPlanned, 3 working days
- 2.1.3Guardrails and nettingFormingPlanned, 2 working days
- 2.1.4Edge forms and blockoutsFormingPlanned, 2 working days
- D-07Rebar deliverySupplierDelivery or inspection, 1 working days
- 2.1.5Bottom rebarRebarPlanned, 2 working days
- 2.1.6Sleeves and embedsPlumbing, electricalPlanned, 1 working days
- 2.1.7Top rebarRebarPlanned, 1 working days
- 2.1.8Pre-pour inspectionInspectorDelivery or inspection, 1 working days
- 2.1.9Pour and finishConcretePlanned, 1 working days
- 2.1.10Cure (no loads)HoldHold, 3 working days
- 2.2Pour 2: layout and formsFormingTentative, 4 working days
- 2.1.11Strip and reshore pour 1Not on this plan yetNot on this plan
- Planned
- Done
- In progress
- Late
- Delivery or inspection
- Open constraint
- Tentative
- Hold
Draft from the master schedule
Activity 2.1 is broken into crew-sized tasks, each with one trade and working-day dates. The rebar delivery and the inspection are tasks too. The pour is planned for day 10, and pour 2 shows up in week 3 as a rough block.
- Two measures from the 2012 study tell you whether the look-ahead itself is working. Tasks Anticipated: how many of this week's tasks were on the look-ahead two weeks ago. Tasks Made Ready: how many tasks on that earlier look-ahead were actually ready and done. Low numbers mean the plan is being made up the week of.
Building it in 3WLA
You can do all of this in a spreadsheet; our free template is a good start. 3WLA does the bookkeeping so the weekly cycle takes minutes.
Spreadsheet
| 2.1.5 | Bottom rebar | Rebar | 2026-11-24 | 2026-11-25 | 0 |
| 2.1.6 | Sleeves and embeds | Plumbing | 2026-11-25 | 2026-11-25 | 0 |
| 2.1.7 | Top rebar | Rebar | 2026-11-26 | 2026-11-26 | 0 |
3WLA schedule
- 2.1.5Bottom rebar · Rebar2 days
- 2.1.6Sleeves and embeds · Plumbing1 day
- 2.1.7Top rebar · Rebar1 day
- Paste Task ID, activity, trade, start, finish and progress straight from Excel; durations follow each project's work week and holidays.
- Status, delay reason, area and notes on every task, so constraints and reasons for misses stay with the work.
- Drag bars on the Gantt to move or stretch tasks, or type a duration to set the finish.
- Issue to a distribution list or a read-only link, with a summary of what changed since the last issue.
- Roll the schedule forward each week instead of rebuilding it; foremen update progress from their phones.
Common questions
How detailed should a 3-week look-ahead be?
Detailed enough that each task is one crew, one area and one to five working days, with a finish you can check on site. Week 3 can be rougher; it firms up as it gets closer.
Who should create the look-ahead?
The superintendent drafts it from the master schedule, and the trade foremen break down and commit to their own work. The project manager or project engineer clears paperwork constraints such as RFIs, submittals and deliveries.
How long does it take to build one?
Expect the first one to take a few hours, mostly breaking activities down and finding constraints. After that, the weekly update (record progress, roll forward, screen the new week 3) is typically under an hour.
What's the difference between a constraint and a predecessor?
A predecessor is work already on the schedule that must finish first. A constraint is something not shown as a task that would stop the work: an unanswered RFI, an unbooked pump, a missing approval.
Can I use Excel to create a look-ahead?
Yes. Download our free template, which fills in the bars and work days for you. When several people edit or subcontractors need the latest version every week, a shared tool like 3WLA saves re-issuing it.
Create your first 3-week look-ahead in 3WLA
Start free with one project and unlimited people. Paste your rows from Excel, mark constraints and delay reasons, issue it to every trade, and roll it forward next week instead of rebuilding it.
Keep reading
- GuideWhat is a 3-week look-ahead schedule?What a 3-week look-ahead schedule is, who prepares it, what goes in it and how it connects to the master schedule, with an annotated example.
- Free template3-week look-ahead template (Excel)Free 3-week look-ahead template for Excel and Google Sheets: a 21-day bar chart that fills itself in, work days, progress and notes. No sign-up.
- GuideHow to run a weekly look-ahead meetingA simple agenda for the weekly look-ahead meeting: who attends, what to review, and how to log constraints and get commitments from every trade.
Sources
- Rethinking Lookahead Planning to Optimize Construction Workflow (Hamzeh, Ballard and Tommelein), Lean Construction Journal, pp. 15–34(opens in a new tab). Lean Construction Institute, 2012.
- Last Planner System® Standard Work(opens in a new tab). Lean Construction Institute, 2023.