Percent Plan Complete explained: why "80% complete" can mean two different things

    On site, "80% complete" can mean four out of five weekly promises kept, or four fifths of the work in place. They're different numbers that answer different questions, and confusing them is how a milestone slips while the team thinks it's winning.

    Updated 14 November 2026 · 6 min read

    This week's commitments · L2 structure

    Percent Plan Complete

    80%

    4 of 5 committed tasks done as promised

    Physical % complete, L2 structure

    30%

    600 of 2,000 labour hours of work in place

    PPC 80% · physical 30%

    Tap tasks to mark them done. Percent Plan Complete counts promises kept this week; physical percent complete measures how much of the work is finished. Four small tasks done out of five is 80% PPC, while the big one, the deck forms, decides how far the slab really moved.

    Quick answer

    Percent Plan Complete (PPC) is the number of weekly tasks completed as promised divided by the number of tasks committed for that week. It measures how reliable your weekly plans are, not how much of the project is built. The Lean Construction Institute puts high-performing teams at 75–90%. Track a reason for every missed task, and keep the weekly tasks tied to the master schedule so high PPC also means real progress.

    Key takeaways

    • PPC = tasks done as promised ÷ tasks committed, counted each week.
    • A task counts only if it's 100% done when promised; 90% is a miss.
    • PPC measures promise reliability; physical % complete measures work in place.
    • High PPC with a slipping milestone means the wrong work is being promised.
    • The reasons behind misses matter more than the number.

    What PPC measures

    LCI defines PPC as "the number of assignments completed on the day stated divided by the total number of assignments made for the week", measuring "the percentage of assignments that are 100% complete as planned." It answers one question: did we do what we said we'd do?

    LCI reports that on traditional projects only about 54% of the work planned for a week gets done that week, and its standard work puts high-performing teams in the 75–90% range.

    How to calculate PPC

    1. List the commitments

      At the weekly meeting, each foreman commits to specific tasks for next week, taken from the look-ahead.

    2. Check at the end of the week

      Mark each task done (100%, on the day promised) or not done. Partly done counts as not done.

    3. Divide

      Done ÷ committed. 13 done out of 18 committed is 72%.

    4. Record a reason for each miss

      Use a fixed list so you can see patterns: prerequisite work, materials, labour, equipment, design, inspection, weather.

    5. Post the trend

      Plot PPC weekly where the whole team can see it.

    PPC is not physical progress

    Physical percent complete measures how much of the work is in place, usually weighted by quantities, hours or cost. PPC counts promises. Five small tasks and one big one are six commitments, but the big one may be most of the work. That's why 80% PPC and 80% complete are different numbers.

    Hamzeh, Ballard and Tommelein (2012) compared weekly PPC with master schedule movement on real projects and found only a weak relationship (correlations of 0.28 and 0.13), including weeks of 100% PPC while the schedule slipped. Their conclusion: when look-ahead planning isn't tied to the master schedule, PPC stops being a reliable indicator of progress.

    PPCSlip

    Weekly PPC 82, 88, 91, 85, 93 and 100 percent; milestone slip 0, 1, 3, 4, 6 and 8 working days.

    Illustrative: six weeks of strong PPC while the milestone forecast slips eight days, because the tasks being promised and kept weren't the ones driving the milestone. Hamzeh, Ballard and Tommelein (2012) saw the same on real projects: weeks at 100% PPC while the schedule slipped, and only a weak correlation between PPC and schedule progress.

    Use the reasons, not just the number

    Group misses by reason over several weeks. A few reasons usually explain most of them, and each points to a constraint to screen harder in the look-ahead.

    • Prerequisite work9 · 28%
    • Materials not available7 · 50%
    • Labour not available5 · 66%
    • Design issue4 · 78%
    • Equipment not available3 · 88%
    • Failed inspection2 · 94%
    • Weather2 · 100%

    Misses · cumulative share

    Illustrative: 32 missed tasks over ten weeks, sorted by reason (categories from LCI's common list). The top three explain two thirds of the misses, so that's where to screen harder.

    Two measures that go with PPC

    Look-ahead and weekly planning measures
    MeasureWhat it answersExample from the 2012 study
    Percent Plan Complete (PPC)Did we do what we promised this week?13 of 18 done: 72%
    Tasks Anticipated (TA)Was this week's work on the look-ahead two weeks ago?14 of 18 anticipated: 78%
    Tasks Made Ready (TMR)Did the work we looked ahead to actually get made ready and done?11 of 20: 55%

    Ways PPC gets gamed (and how to avoid it)

    • Committing only to easy work. Pull weekly tasks from the critical work on the look-ahead.
    • Counting partly done tasks. Only 100% done on the day counts.
    • Adding tasks after the fact. Commitments are fixed at the weekly meeting.
    • Splitting work into tiny tasks. Keep tasks crew-sized: a few days each.

    Tracking it in 3WLA

    • Each task has progress (0–100%), status and a delay reason, updated from the office or a phone.
    • Group the schedule by status or trade to see what was done and what slipped this week.
    • Each issue records what changed since the last one, so commitments and changes are on record.
    • Export to CSV to chart PPC and reasons over time.

    Common questions

    What is a good PPC?

    LCI's standard work puts high-performing teams at 75–90%. Consistently 100% can mean the team is only committing to easy work.

    Does PPC measure project progress?

    No. It measures how reliably weekly promises are kept. Physical percent complete and the master schedule forecast measure progress.

    Is a task that's 90% done counted?

    No. PPC only counts tasks that are 100% complete on the day promised.

    Where does PPC come from?

    It's part of the Last Planner System developed by Glenn Ballard and Greg Howell and promoted by the Lean Construction Institute.

    Track weekly commitments and reasons in 3WLA

    Every look-ahead task carries progress, status and a delay reason, updated from site. See what slipped and why before the next meeting, and issue the new plan to every trade. Free for one project, with unlimited people.

    Sources

    1. Last Planner System® Standard Work(opens in a new tab). Lean Construction Institute, 2023.
    2. The Last Planner System: From Pull Planning to Weekly Work Planning(opens in a new tab). Lean Construction Institute.
    3. Rethinking Lookahead Planning to Optimize Construction Workflow (Hamzeh, Ballard and Tommelein), Lean Construction Journal, pp. 15–34(opens in a new tab). Lean Construction Institute, 2012.