Percent Plan Complete explained: why "80% complete" can mean two different things
On site, "80% complete" can mean four out of five weekly promises kept, or four fifths of the work in place. They're different numbers that answer different questions, and confusing them is how a milestone slips while the team thinks it's winning.
Updated 14 November 2026 · 6 min read
This week's commitments · L2 structure
Percent Plan Complete
80%
4 of 5 committed tasks done as promised
Physical % complete, L2 structure
30%
600 of 2,000 labour hours of work in place
PPC 80% · physical 30%
Quick answer
Percent Plan Complete (PPC) is the number of weekly tasks completed as promised divided by the number of tasks committed for that week. It measures how reliable your weekly plans are, not how much of the project is built. The Lean Construction Institute puts high-performing teams at 75–90%. Track a reason for every missed task, and keep the weekly tasks tied to the master schedule so high PPC also means real progress.
Key takeaways
- PPC = tasks done as promised ÷ tasks committed, counted each week.
- A task counts only if it's 100% done when promised; 90% is a miss.
- PPC measures promise reliability; physical % complete measures work in place.
- High PPC with a slipping milestone means the wrong work is being promised.
- The reasons behind misses matter more than the number.
What PPC measures
LCI defines PPC as "the number of assignments completed on the day stated divided by the total number of assignments made for the week", measuring "the percentage of assignments that are 100% complete as planned." It answers one question: did we do what we said we'd do?
LCI reports that on traditional projects only about 54% of the work planned for a week gets done that week, and its standard work puts high-performing teams in the 75–90% range.
How to calculate PPC
List the commitments
At the weekly meeting, each foreman commits to specific tasks for next week, taken from the look-ahead.
Check at the end of the week
Mark each task done (100%, on the day promised) or not done. Partly done counts as not done.
Divide
Done ÷ committed. 13 done out of 18 committed is 72%.
Record a reason for each miss
Use a fixed list so you can see patterns: prerequisite work, materials, labour, equipment, design, inspection, weather.
Post the trend
Plot PPC weekly where the whole team can see it.
PPC is not physical progress
Physical percent complete measures how much of the work is in place, usually weighted by quantities, hours or cost. PPC counts promises. Five small tasks and one big one are six commitments, but the big one may be most of the work. That's why 80% PPC and 80% complete are different numbers.
Hamzeh, Ballard and Tommelein (2012) compared weekly PPC with master schedule movement on real projects and found only a weak relationship (correlations of 0.28 and 0.13), including weeks of 100% PPC while the schedule slipped. Their conclusion: when look-ahead planning isn't tied to the master schedule, PPC stops being a reliable indicator of progress.
Weekly PPC 82, 88, 91, 85, 93 and 100 percent; milestone slip 0, 1, 3, 4, 6 and 8 working days.
Use the reasons, not just the number
Group misses by reason over several weeks. A few reasons usually explain most of them, and each points to a constraint to screen harder in the look-ahead.
- Prerequisite work9 · 28%
- Materials not available7 · 50%
- Labour not available5 · 66%
- Design issue4 · 78%
- Equipment not available3 · 88%
- Failed inspection2 · 94%
- Weather2 · 100%
Misses · cumulative share
Two measures that go with PPC
| Measure | What it answers | Example from the 2012 study |
|---|---|---|
| Percent Plan Complete (PPC) | Did we do what we promised this week? | 13 of 18 done: 72% |
| Tasks Anticipated (TA) | Was this week's work on the look-ahead two weeks ago? | 14 of 18 anticipated: 78% |
| Tasks Made Ready (TMR) | Did the work we looked ahead to actually get made ready and done? | 11 of 20: 55% |
Ways PPC gets gamed (and how to avoid it)
- Committing only to easy work. Pull weekly tasks from the critical work on the look-ahead.
- Counting partly done tasks. Only 100% done on the day counts.
- Adding tasks after the fact. Commitments are fixed at the weekly meeting.
- Splitting work into tiny tasks. Keep tasks crew-sized: a few days each.
Tracking it in 3WLA
- Each task has progress (0–100%), status and a delay reason, updated from the office or a phone.
- Group the schedule by status or trade to see what was done and what slipped this week.
- Each issue records what changed since the last one, so commitments and changes are on record.
- Export to CSV to chart PPC and reasons over time.
Common questions
What is a good PPC?
LCI's standard work puts high-performing teams at 75–90%. Consistently 100% can mean the team is only committing to easy work.
Does PPC measure project progress?
No. It measures how reliably weekly promises are kept. Physical percent complete and the master schedule forecast measure progress.
Is a task that's 90% done counted?
No. PPC only counts tasks that are 100% complete on the day promised.
Where does PPC come from?
It's part of the Last Planner System developed by Glenn Ballard and Greg Howell and promoted by the Lean Construction Institute.
Track weekly commitments and reasons in 3WLA
Every look-ahead task carries progress, status and a delay reason, updated from site. See what slipped and why before the next meeting, and issue the new plan to every trade. Free for one project, with unlimited people.
Keep reading
- GuideWhy look-ahead schedules fail: 7 constraintsSeven constraints to check before work starts: drawings, materials, labour, equipment, access, prior work and approvals, plus how a constraint log clears them.
- GuideHow to run a weekly look-ahead meetingA simple agenda for the weekly look-ahead meeting: who attends, what to review, and how to log constraints and get commitments from every trade.
- GuideWhat is a 3-week look-ahead schedule?What a 3-week look-ahead schedule is, who prepares it, what goes in it and how it connects to the master schedule, with an annotated example.
Sources
- Last Planner System® Standard Work(opens in a new tab). Lean Construction Institute, 2023.
- The Last Planner System: From Pull Planning to Weekly Work Planning(opens in a new tab). Lean Construction Institute.
- Rethinking Lookahead Planning to Optimize Construction Workflow (Hamzeh, Ballard and Tommelein), Lean Construction Journal, pp. 15–34(opens in a new tab). Lean Construction Institute, 2012.